Commencement of Replacement Construction on Eurus Kamaishi Wind Farm
Eurus Energy Kamaishi LLC, a group company of Eurus Energy Holdings Corporation, started reconstruction work on August 1st at Eurus Kamaishi Wind Farm, which had been operating in Kamaishi City, Tono City and Otsuchi Town in Iwate Prefecture.
The facility, which began commercial operation in December 2004 and had operated for nearly 20 years, temporarily terminated operation in March 2023 for the complete reconstruction work.
In the replacement project, 43 wind turbines (single output capacity of 1.0 MW) will be reconstructed with 11 wind turbines (single output capacity of 4.2 MW/ Vestas), one of the largest models in Japan. The wind farm will continue to effectively utilize abundant wind resources and contribute to the revitalization of the community.
Commercial operation is scheduled to start in April 2026, and all electricity generated will continue to be sold to the Tohoku Electric Power Network Co., Inc. The generated power is equivalent to the electricity consumed by approximately 31,000 average households, and is expected to reduce CO2 emissions by approximately 44,000 tons per year.
Eurus Energy Group will proceed with the replacement work with the understanding and cooperation of local residents and other parties, while giving full consideration to environmental preservation and placing the highest priority on safety management.
Based on our corporate philosophy of "playing a role in global environmental conservation through the diffusion and expansion of clean energy", Eurus Energy Group will continue to contribute to global environmental conservation and the creation of a sustainable society through the introduction and expansion of renewable energy by making efforts to promote and value the appeal of renewable energy.
【Outline of the Project】
Project name |
Eurus Kamaishi Wind Farm |
|
Location |
Kamaishi City, Tono City and Otsuchi Town, Iwate Prefecture |
|
Total output |
Before the replacement |
After the replacement |
最新のPress Release/News
-
Release
2025.02.14
Eurus Energy Starts Operation of Ashikawa Wind Farm
-107 Wind Turbines of Dohoku Wind Power Generation Project Completed – -
Release
2025.02.10
Eurus Technical Service to Start Providing O&M Service for Onshore Wind Power Plants
– Helping to Resolve Issues in the Wind Power Generation Business with the Know-How of Japan’s No.1 Wind Power Generation Company – -
Release
2025.02.03
Eurus Energy Starts Operation of Yuchi Wind Farm
– The Fifth Wind Farm of the Dohoku Wind Power Generation Project Completed – -
Projects
2024.11.28
Eurus Energy Holds Opening Ceremony for the Eurus Sandaimyojin Wind Farm