Eurus Energy Holds Opening Ceremony for the Kawanishi Wind Farm

  • Projects
2024.05.22

Eurus Energy held an opening ceremony for the Kawanishi Wind Farm on May 21, which was constructed by Dohoku Wind Farm LLC, a group company of Eurus Energy Holdings, and started operation on January 15, 2024. Local government officials, community members and construction partners attended the ceremony to pray for the safe operation of the wind farm.

The Kawanishi Wind Farm is a part of the Dohoku Wind Power Generation Project, which will install a total of 107 wind turbines at a total of six wind farms in the northern Hokkaido area and the third wind farm following the Hamasato Wind Farm and the Kawaminami Wind Farm. The Kawanishi Wind Farm consists of 15 Siemens Gamesa Renewable Energy S.A. wind turbines with an output of 4.3 MW, one of the largest in Japan. All electricity generated will be sold to Hokkaido Electric Power Network Inc.

Based on our corporate philosophy of “Helping to preserve the global environment by disseminating and expanding clean energy technologies” and our corporate vision of “Develop with local communities and maintain the trust of society”, Eurus Energy group will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.

 

【Outline of the Project

Name of the project Kawanishi Wind Farm
Location Wakkanai City and Toyotomi Town, Hokkaido
Capacity 64MW (4.3MW×15 / Siemens Gamesa Renewable Energy S.A. / Output control to 64MW)
EPC OBAYASHI CORPORATION
Start of construction August, 2020
Start of operation January 15, 2024
Purchaser Hokkaido Electric Power Network, Inc.