Eurus Energy Begins Construction of Eurus Odanosawa Wind Farm I & II
Expansion and Replacement of Eurus Odanosawa Wind Farm Scheduled to Begin Operation in March 2027
Eurus Energy Holdings Corporation (“Eurus Energy") announced today that Eurus Energy Odanosawa LLC, a group company of Eurus Energy, has begun construction of Eurus Odanosawa Wind Farm I & II (capacity: 43MW)" in Higashidoori Village, Shimokita District, Aomori Prefecture on September 2, 2024.
The Eurus Odanosawa Wind Farm (capacity: 13MW), which started operation in October 2004 and is currently operating in the Odanosawa district of Higashidoori, has operated for nearly 20 years and is scheduled to terminate operation in July 2025 for the complete reconstruction work.
Eurus Odanosawa Wind Farm I & II will expand and reconstruct the Eurus Odanosawa Wind Farm. The expansion project, which began today, will involve the installation of seven Siemens Gamesa Renewable Energy S.A. wind turbines, each with an output of 4.3 MW, one of the largest in Japan. The replacement project will involve reconstructing ten 1.3MW wind turbines with three 4.3MW wind turbines. Commercial operation is scheduled to start in March 2027, and the generated power will be equivalent to the electricity consumed by approximately 21,000 average households, and is expected to reduce CO2 emissions by approximately 42,000 tons per year.*1 The wind farms will continue to effectively utilize abundant wind resources and contribute to the revitalization of the community.
Based on our corporate philosophy of “Helping to preserve the global environment by disseminating and expanding clean energy technologies” and our corporate vision of “Develop with local communities and maintain the trust of society”, Eurus Energy group will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.
*1 Calculated from the CO2 emission factor (FY2024) of Tohoku Electric Power Co., Inc.
【Outline of the Project】
Name of the project | Eurus Odanosawa Wind Farm I & II | |
Location | Odanosawa, Higashidoori Village, Shimokita District, Aomori Prefecture | |
EPC | Kandenko Co., Ltd. | |
Wind turbine manufacturer | Siemens Gamesa Renewable Energy S.A. | |
Capacity | 43MW (4.3MW×10) | |
Expansion | Replacement | |
30.1MW (4.3MW×7) | 12.9MW (4.3MW×3) | |
Start of construction | September 2024 | September 2024 (preparation work) April 2025 (partial removal begins) |
Start of operation | March, 2027 (planned) |
Name of the project | Eurus Odanosawa Wind Farm |
Location | Odanosawa, Higashidoori Village, Shimokita District, Aomori Prefecture |
Wind turbine manufacturer | Siemens Gamesa Renewable Energy S.A. (previously Bonus Energy A/S) |
Capacity | 13MW (1.3MW×10) |
Start of construction | July, 2003 |
Start of operation | October, 2004 to July, 2025 (planned) |
最新のPress Release/News
-
Release
2024.10.03
Eurus Energy and Terras Energy to be Integrated
-
Release
2024.09.24
Eurus Energy Starts Verification Test to Improve Wind Power Generation Efficiency
– Attach Nikon’s Riblet Film to Wind Turbine Blades – -
Release
2024.09.02
Eurus Energy Begins Construction of Eurus Odanosawa Wind Farm I & II
Expansion and Replacement of Eurus Odanosawa Wind Farm Scheduled to Begin Operation in March 2027 -
Release
2024.08.29
Eurus Energy Starts Operation of Eurus Sandaimyojin Wind Farm