Ground Breaking Ceremony held for Eurus Tokoro-Notoro Wind Farm
The ground breaking ceremony was held on April 21st for Eurus Energy Group’s Eurus Tokoro-Notoro Wind Farm project, which will be developed in Kitami City and Abashiri City, Hokkaido. The ceremony was held in Tokoro Town, Kitami City, with the presence of local government officials and construction participants.
This wind farm will consist of seven Siemens Gamesa Renewable Energy 4.3MW wind turbines, to be located in the vicinity of the town of Tokoro and Notoro.
All electricity generated will be sold to Hokkaido Electric Power Network, Inc.
The wind farm is scheduled to commence commercial operation in April 2024, and expected to supply electricity equivalent to power approximately 20,000 average households while reducing CO2 emissions by approximately 34,000 tons per year.
【Outline of the Project】
Project name | Location | Total output |
Eurus Tokoro-Notoro Wind Farm | Kitami City and Abashiri City, Hokkaido | 27.35MW (with output control) (4.3MW×7unit / Siemens Gamesa Renewable Energy) |
最新のPress Release/News
-
Projects
2024.07.24
Eurus Energy Holds Opening Ceremony for the Eurus Tokoro-Notoro Wind Farm
-
Release
2024.06.18
Eurus Energy Announces Investment in Offshore Wind Power Generation Project in Scotland
– Eurus Energy Group’s First Investment in Offshore Wind Power Generation Project – -
Release
2024.05.29
Eurus Energy and Windlab Start Operation of Kennedy Energy Park in Australia
– Eurus Energy Group’s First Large-scale Hybrid Renewable Energy Facility – -
Projects
2024.05.24
Eurus Energy Holds Opening Ceremony for the Kabaoka Wind Farm