Eurus Energy Holds Opening Ceremony for Ashikawa Wind Farm

  • Projects
2025.05.27

Eurus Energy held an opening ceremony for the Ashikawa Wind Farm on May 27, which were constructed by Dohoku Wind Farm LLC, a group company of Eurus Energy Holdings Corporation, and started operation on February 14, 2025. Local government officials, community members and construction partners attended the ceremony to pray for the safe operation of the wind farm.

The Ashikawa Wind Farm is a part of the Dohoku Wind Power Generation Project, which installs a total of 107 wind turbines at a total of six wind farms in the northern Hokkaido area and the sixth wind farm.
The Ashikawa Wind Farm consists of 31 Siemens Gamesa Renewable Energy S.A. wind turbines with an output of 4.3 MW, one of the largest in Japan. All electricity generated is sold to Hokkaido Electric Power Network Inc.

Based on our corporate philosophy of “Helping to preserve the global environment by disseminating and expanding clean energy technologies” and our corporate vision of “Develop with local communities and maintain the trust of society”, Eurus Energy group will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.

 

【Outline of the Project

Name of the project Ashikawa Wind Farm
Location Toyotomi Town, Hokkaido
Capacity 128.8 MW
(4.3 MW×31 / Siemens Gamesa Renewable Energy S.A.)
EPC SHIMIZU CORPORATION
Start of construction North section: March 2020
South section: April, 2020
Start of operation North section: January 4, 2024
South section: February 14, 2025
Purchaser Hokkaido Electric Power Network, Inc.