Press ReleaseProjects

Eurus Energy Participates in Its Third Wind Power IPP Project in Egypt with 900 MW Capacity

Eurus Energy Holdings Corporation (“Eurus Energy”) announced today that AEOLUS SAS (“AEOLUS”), a joint venture between Eurus Energy and CFAO SAS, will participate in its third wind power independent power producer (“IPP”) project (“the Project”) in the Arab Republic of Egypt (“Egypt”).

The Project involves the construction, ownership and operation of the 900 MW Gulf of Suez Wind Farm III in the Gulf of El Zayt area along the Gulf of Suez. The Project will be undertaken through Shokeir Wind Energy S.A.E. (“Shokeir Wind Energy”), a local project company jointly owned by AEOLUS, France-based independent power producer ENGIE S.A. (“ENGIE”) and Egyptian construction and development company Orascom Construction PLC (“Orascom Construction”).

Commissioning of the first 300 MW is scheduled to begin in January 2028, followed by the phased commencement of commercial operation, with full commercial operation planned for September 2028. The generated electricity will be sold to the Egyptian Electricity Transmission Company under a 25-year power purchase agreement. It is expected to generate electricity equivalent to the annual power consumption of approximately 2.2 million Egyptian households and reduce CO2 emissions by approximately 1.5 million tons per year.

Through AEOLUS, the Eurus Energy Group is currently involved in two wind power projects in Egypt, Gulf of Suez Wind Farm I and Gulf of Suez Wind Farm II, with a combined capacity of 912.5 MW. Upon completion of Gulf of Suez Wind Farm III, the three wind farms will have a combined capacity of 1,812.5 MW.

The Egyptian government has set a target of increasing the share of renewable energy to 42% of total power generation by 2030. Through the expansion of renewable energy generation in Egypt, the Eurus Energy Group will contribute to the achievement of the government’s goal and the country’s economic development.

The Eurus Energy Group will contribute to the spread of clean and low-cost renewable energy in Africa through AEOLUS and continue its efforts to further expand wind and solar power generation, thereby helping to conserve the global environment and create a sustainable society.

Construction Site
pressen_20261112.webp

Outline of the Project

Project nameGulf of Suez Wind Farm III
Operating company nameShokeir Wind Energy S.A.E.
LocationGulf of El Zayt, Arab Republic of Egypt

Business description

Wind power generation and sale of electricity
Investment ratioAEOLUS SAS: 40%; ENGIE S.A.: 35%; Orascom Construction PLC: 25%
Grid connection capacity900 MW (10.5 MW × 86)
Electricity purchaserEgyptian Electricity Transmission Company
Financing institutions

Japan Bank for International Cooperation (JBIC), Proparco, FMO, Société Générale, Crédit Agricole CIB and KfW IPEX-Bank
(Financing provided by commercial financial institutions will be covered by insurance from Nippon Export and Investment Insurance (NEXI)).

Start of commercial operation

Planned for September 2028


Overview of AEOLUS

Company nameAEOLUS SAS
EstablishmentMarch 13, 2024
LocationFrench Republic
RepresentativePresident and Managing Director Hideharu Toba
Business activitiesRenewable energy business
Investment ratioCFAO 50%, Eurus Energy 50%