Eurus Energy Commences Commercial Operation of Hajang 5 Wind Power in South Korea

Eurus Energy Holdings Corporation (“Eurus Energy”) announced today that Eurus Energy Korea Corporation, a group company of Eurus Energy, commenced commercial operation of the Hajang 5 Wind Power, a 13.5 MW wind power plant located in Taebaek and Samcheok, Gangwon-do, South Korea, on October 30, 2026.

presssen_20261111.webp

The wind farm is the Eurus Energy Group’s fifth wind farm in South Korea. Three wind turbines manufactured by ENERCON GmbH, each with a capacity of 4.5 MW, are installed in a mountainous region at an elevation of approximately 1,080 meters.

All electricity generated by the wind farm will be sold to Korea District Heating Corporation under a 20-year power purchase agreement. It is expected to generate electricity equivalent to the power consumption of approximately 13,000 households and reduce CO2 emissions by approximately 20,000 tons per year.

Based on our corporate philosophy of “Helping to preserve the global environment by disseminating and expanding clean energy technologies” and our corporate vision of “Develop with local communities and maintain the trust of society,” the Eurus Energy Group will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.

Outline of the Project

Project nameHajang 5 Wind Power
LocationTaebaek and Samcheok, Gangwon-do, South Korea
Capacity13.5 MW(4.5 MW × 3 / ENERCON GmbH)
Operating company nameHajang 5 Wind Power Co., Ltd.
InvestorsEurus Energy Korea Corporation
Wind EM Energy Co., Ltd.
EPCWind EM Energy Co., Ltd.
Daehan Green Energy Co., Ltd.
Start of constructionMay 2025
Start of operationOctober 2026
PurchaserKorea District Heating Corporation