Eurus Energy Holds Opening Ceremony for Eurus Kamaishi Wind Farm
Eurus Energy Holdings Corporation ("Eurus Energy") held an opening ceremony for the Eurus Kamaishi Wind Farm on May 22, which were constructed by Eurus Energy Kamaishi LLC, a group company of Eurus Energy, and started operation on March 1, 2026. Local government officials, community members and construction partners attended the ceremony to pray for the safe operation of the wind farm.
The Eurus Kamaishi Wind Farm, which started commercial operation in December 2004 and has been in operation for nearly 20 years, terminated operation in March 2023, and complete reconstruction work has been carried out since then. In the replacement project, 43 wind turbines manufactured by Mitsubishi Heavy Industries, Ltd. (single output capacity: 1.0 MW) were replaced with eleven wind turbines manufactured by Vestas Wind Systems A/S (single output capacity: 4.2 MW).
Based on our corporate philosophy of "Helping to preserve the global environment by disseminating and expanding clean energy technologies" and our corporate vision of "Develop with local communities and maintain the trust of society", Eurus Energy group will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.
Outline of the Project
| Project Name | Eurus Kamaishi Wind Farm |
|---|---|
| Location | Kamaishi City, Tono City, Otsuchi Town, Iwate Prefecture |
| Capacity | Before the replacement: 42.9 MW(1.0 MW × 43 / Mitsubishi Heavy Industries, Ltd. ) After the replacement: 42.9 MW(4.2 MW × 11 / Vestas Wind Systems A/S) |
| EPC | Shimizu–Kinden Specified Construction Joint Venture |
| Start of construction | August 2023 |
| Start of operation | March 1, 2026 |
| Purchaser | Tohoku Electric Power Network Co., Inc. |