NewsProjects

Start of Operation for Ariette Battery Installation, The Netherlands

Eurus Energy Europe BV and Toyota Tsusho Europe SA proudly announce the successful commissioning and start of operation of the ‘Ariette’ battery project. This containerised battery energy storage system (BESS) has a capacity of 1 MW and 2.5 MWh. The BESS is co-located with the Eurus-owned ‘Windpark Mondriaan’ near Delfzijl, The Netherlands. By sharing a grid connection with the windfarm, the BESS makes optimal use of existing infrastructure. It will provide various services to grid operators and mitigate energy imbalance on the electricity grid, facilitating wider deployment of renewable energy generation.

news_20250324.webp


Outline of the Project

Project NameAriette Battery Energy Storage System
LocationFarmsum, Groningen, The Netherlands
LandownerGroningen Seaports
Rated power1 MW
Capacity2.5 MWh
Battery IntegratorFreqcon
ContractorsAlsema / Koninklijke Sjouke Dijkstra
TraderScholt
Start of constructionDecember 2023
Start of operationMarch 24, 2025