Eurus Energy Starts Operation of Eurus Sandaimyojin Wind Farm

Eurus Energy Holdings Corporation (“Eurus Energy”) announced today that Eurus Sandai Myojin Wind Farm LLC, a group company of Eurus Energy, has completed construction of the Eurus Sandaimyojin Wind Farm (capacity: 34 MW) in Iwaki City, Fukushima, and its commencement of commercial operation on August 29, 2024.

press_20240829.webp

The Eurus Sandaimyojin Wind Farm is Eurus Energy Group’s third wind farm in Fukushima Prefecture and consists of nine Vestas wind turbines installed along a ridge line of 600 to 800 meters mountains, including Mt. Sandaimyojin. Each wind turbine has a single unit output of 4.2 MW, which is one of the highest capacity onshore models in Japan. All electricity generated will be sold to Tohoku Electric Power Network Co., Inc. It is expected to generate electricity equivalent to the power consumption of approximately 16,000 average households and reduce CO2 emissions by 33,000 tons per year*1.

Based on our corporate philosophy of “Helping to preserve the global environment by disseminating and expanding clean energy technologies” and our corporate vision of “Develop with local communities and maintain the trust of society”, Eurus Energy group will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.

  1. *1Calculated from the CO2 emission factor (FY2022) of Tohoku Electric Power Co., Inc.


Outline of the Project

Project NameEurus Sandaimyojin Wind Farm
LocationIwaki City, Fukushima
Capacity34 MW (4.2 MW × 9 / Vestas)
EPCKAJIMA CORPORATION
Start of constructionSeptember 2021
Start of operationAugust 29, 2024
PurchaserTohoku Electric Power Network Co., Inc.


Contact