Eurus Energy Starts Operation of Ashikawa Wind Farm
-107 Wind Turbines of Dohoku Wind Power Generation Project Completed –

2025.02.14

Eurus Energy Holdings Corporation (“Eurus Energy”) announced today that Dohoku Wind Farm LLC, a group company of Eurus Energy, has completed construction of the south section of the Ashikawa Wind Farm (capacity: 128.8 MW) in Toyotomi Town, Hokkaido, and together with the north section in operation, all sections of the wind farm commence commercial operation on February 14, 2025.

The Wind Farm is a part of the Dohoku Wind Power Generation Project, which will install a total of 107 wind turbines at a total of six wind farms in the northern Hokkaido area and the sixth wind farm following the Hamasato Wind Farm, the Kawaminami Wind Farm, the Kawanishi Wind Farm, the Kabaoka Wind Farm, and the Yuchi Wind Farm. With the commencement of commercial operations of the Ashikawa Wind Firm, the Dohoku Wind Power Generation Project has been completed as planned, and the total capacity of the project has reached 434.5MW.

While the northern Hokkaido is one of Japan’s most suitable areas for wind power generation due to its favorable wind conditions, the lack of sufficient transmission line capacity to deliver electricity to demand areas presented a challenge to development in the region. Thus, in order to promote the introduction of large-scale wind farms in the area, Eurus Energy along with partner companies established the North Hokkaido Wind Energy Transmission Corporation, which began commercial operation of government-subsidized large-scale power grid and storage battery facilities in April 2023.

The Ashikawa Wind Farm consists of 31 Siemens Gamesa Renewable Energy S.A. wind turbines with an output of 4.3 MW, one of the largest in Japan. All electricity generated will be sold to Hokkaido Electric Power Network Inc. It is expected to generate electricity equivalent to the power consumption of approximately 76,000 average households and reduce CO2 emissions by 142,000 tons per year*1.

Based on our corporate philosophy of "Helping to preserve the global environment by disseminating and expanding clean energy technologies" and our corporate vision of "Develop with local communities and maintain the trust of society", Eurus Energy will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.

1  Calculated from the CO2 emission factor (FY2022) of Hokkaido Electric Power Co.,Inc.

Outline of the Project

Name of the project

Ashikawa Wind Farm

Location

Toyotomi Town, Hokkaido

Capacity

128.8MW(4.3MW×31 / Siemens Gamesa Renewable Energy S.A.)

EPC

SHIMIZU CORPORATION

Start of construction

North section: March 2020

South section: April 2020

Start of operation

North section: January 4, 2024

South section: February 14, 2025

Purchaser

Hokkaido Electric Power Network, Inc.