Eurus Energy Holds Opening Ceremony for the Eurus Sandaimyojin Wind Farm

  • Projects
2024.11.28

Eurus Energy held an opening ceremony for the Eurus Sandaimyojin Wind Farm on November 27, which was constructed in Iwaki City, Fukushima Prefecture by Eurus Sandai Myojin Wind Farm LLC, a group company of Eurus Energy Holdings, and started operation on August 29, 2024. Local government officials, community members and construction partners attended the ceremony to celebrate the successful construction and wish for the continued safe operation of the wind farm.

The Eurus Sandaimyojin Wind Farm is Eurus Energy Group’s third wind farm in Fukushima Prefecture and consists of nine Vestas wind turbines installed along a ridge line of 600 to 800 meters mountains, including Mt. Sandaimyojin. Each wind turbine has a single unit output of 4.2 MW, which is one of the highest capacity onshore models in Japan. All electricity generated will be sold to Tohoku Electric Power Network Co., Inc.

Based on our corporate philosophy of “Helping to preserve the global environment by disseminating and expanding clean energy technologies” and our corporate vision of “Develop with local communities and maintain the trust of society”, Eurus Energy group will continue to work on further expansion of wind power generation and contribute to global environmental conservation and the creation of a sustainable society.

【Outline of the Project

Name of the project Eurus Sandaimyojin Wind Farm
Location Iwaki City, Fukushima
Capacity 34MW (4.2MW×9 / Vestas / Output control to 34MW)
EPC KAJIMA CORPORATION
Start of construction September, 2021
Start of operation August 29, 2024
Purchaser Tohoku Electric Power Network Co., Inc.